MaitrioATMP DASHBOARD31 Aug 2026
Maitrio ATMP Dashboard · synthetic operating data

ATMP release control tower

One decision view for tool hook-up, facility dependencies, evidence and recovery.

24↑ 3 versus last week
1250% of window
74 need decision
91%↑ 4.2 pts this week
186 overdue

Release window — next 7 days

Click a tool to trace its readiness decision.

Tool release readiness

ATMP-014 · WFI Skid 01 · at risk

68%
2
blocking conditions
Release forecast: 05 Sep
Decision required by 16:00 todayApprove vendor overtime for loop testing or accept a one-day release shift.
  • Facility utilities✓ 100%
  • Materials & long-lead✓ 94%
  • QA evidence / ITRs! 67%
  • Safety clearance! Pending

Priority recovery actions

Ranked by release impact.

Contractor commitments

This week · accountable delivery

ContractorOn trackOpen
Sterling & Wilson92%2
Aitech Engineering78%5
Vector Process69%7
BioClean Systems88%3

Program signal

What leadership needs to know.

12Released
5Hook-up
4QA pending
3Blocked
₹1.6 CrRisk exposure
98%Update compliance
Tool-to-utility dependency model

Tool readiness register

Every tool carries its hook-up scope, gates, evidence and release conditions.

Tool / workfrontAreaContractorReadinessRelease gateStatus
Spatial release visibility

Facility & tool map

Click a tool to open its exact readiness, evidence and recovery path.

● On track● At risk● Blocked

UPW Production

Assembly Bay B1

Gas Farm

Cleanroom East

Assembly Bay B2

Facility services

Power, exhaust and material sources are connected through the Maitrio readiness graph.
How to use this in the demoStart with the red tool, show the blockers in its drill-down, then open the release-impact simulator to explain how one decision affects the facility plan.
Contractor mobile / web workflow

Field update queue

Capture a structured update once, then route it for validation and action.

Assigned today

Updates automatically affect release readiness.

Demo workflow

The operational loop, from field proof to release.

1. CaptureProgress, photo, checklist, blocker
2. ValidatePMC reviews changes
3. DecideEscalate trade-offs
4. RecoverAssign owner + date
5. ReleaseEvidence pack locks gate
Demo interactionSubmit a field update and the toast confirms the record was routed to the responsible PMC lead.
Delivery accountability

Contractor performance

Performance is evaluated against the workfronts and release dates they influence.

ContractorDisciplineWorkfrontsScheduleQualitySafetyRelease impact
Sterling & WilsonHVAC / Exhaust892%90%96%On track
Aitech EngineeringMechanical678%86%92%2 at risk
Vector ProcessPiping / UPW769%83%90%3 blocked
BioClean SystemsCleanroom / ESD588%94%95%On track
Evidence-driven turnover

Quality & turnover gates

Evidence is connected to a specific tool and its release decision.

ATMP-014 evidence pack

Two conditions prevent release.

✓ Mechanical completion certificateApproved
✓ UPW point-of-use purity testApproved
! Loop pressure test / ITR-204Due today
! Safety clearance / PTW closePending
✓ As-built mark-upApproved

Turnover completeness

Release work packages, next 14 days

76%
18 packages
8 ready · 6 QA pending · 4 blocked

Focus: QA evidence
Decision intelligence

Executive decision brief

Risk is expressed in terms of release consequence and the next required decision.

68%Target ≥ 90%
153 critical
117 progressing
98%Daily source updates
14Next 4 weeks

Decisions & asks

Items that cannot be solved by a field user.

1
Approve temporary test window for WFI Skid 01Protects 05 Sep tool release · owner: PMC Project Manager
2
Authorize vendor overtime for electrical loop testingProtects two affected tools · cost impact: ₹3.8L
3
Approve expedited cable-tray deliveryPrevents current material blocker from becoming a release delay

Connected data position

Maitrio adds a decision layer above the customer’s existing records.

  • Completion recordsReady to sync
  • Master scheduleMilestones in
  • Procurement dataMaterial signal in
  • MaitrioTool readiness + recovery
  • Executive teamDecision brief out
Deliberate differentiationExisting systems record progress; Maitrio makes the release dependency, owner and next decision explicit.
Tools / UPW Production / ATMP-014

WFI Skid 01

ATMP-014 · UPW Production · Vector Process

At risk
Site ready27 Aug
Mechanical28 Aug
Electrical29 Aug
Utility testIn progress
QA verifyPending
Release05 Sep

Dependency readiness

Calculated at tool-connection level.

ConditionReadinessEvidence / issue
UPW connection100%POU test approved
Electrical power100%Load test complete
Vacuum & exhaust75%Pressure ITR pending
Materials94%Gasket ETA 31 Aug
Safety gate50%PTW closure pending

Open actions

!
Complete pressure ITR-204Owner: Aitech Engineering · Due today
!
Close PTW and EHS clearanceOwner: Safety team · Due 31 Aug

Release verdict

Live explanation—not a manual RAG.

68%
Conditional

2 blockers remain.
Tool cannot be released until QA ITR and safety clearance are signed.